Mbale
Building Watch
Unfinished brick and concrete house left under construction

Independent contractor warning

Do not use
Queue Contractors
Limited.

Families in Mbale who paid Queue Contractors Limited to build their homes say they were left with unfinished buildings, money gone and nowhere to live. Read their experience before you hand over a deposit.

What clients report
Mbale City, UgandaConstruction & contractor checks

Paid in full. Left with nothing.

Clients describe the same pattern: money taken, work stopped, the company unreachable, and families still waiting for homes they have already paid for.

Money taken

Clients report paying for materials and labour, after which the company stopped answering.

Gone for months

Clients describe months with no one on site, and a new excuse each time they chase progress.

Builds abandoned

Homes are reported left half-built and unfit to live in, long after payment was made.

Families homeless

Some families say they gave up rented homes for builds that were never finished, and now have nowhere to live.

Dan Mukwana
Dan Mukwana, named in public reporting as the engineer at Queue Contractors Limited.

Engineer Dan Mukwana

Public reporting identifies Dan Mukwana as the engineer at Queue Contractors Limited in Mbale. Clients who dealt with him directly describe the same conduct again and again.

Identified by Uganda Radio Network ↗ His Facebook profile, for right of reply ↗
  • Breach of contractClients say agreed work, timelines and terms were not honoured.
  • Money taken up frontClients report paying in advance, after which the work did not follow.
  • DisappearingOnce paid, clients say he became unreachable for long periods.
  • DishonestyClients describe false assurances and repeated explanations that turned out to be untrue.
  • Unprofessional conductClients describe angry, disrespectful responses when they asked about progress.
  • Money lostMultiple clients say they lost the money they paid and never received the finished work.

Building in Mbale: the context

12.6%
General compliance of building operations with the Building Control Act, Regulations and Code, measured nationally in FY 2023/24.NBRB annual report ↗
~110 sq mi
Mbale City’s current extent, against a physical development plan covering about 55 square miles.Daily Monitor, May 2026 ↗
Before concrete
Under the Building Control Act, inspectors are expected to verify foundations and steel reinforcement before concrete is poured.Daily Monitor, May 2026 ↗

Red flags on any build

Common patterns to watch for when hiring a builder or engineer in Mbale. None of these alone proves wrongdoing, but together they call for caution.

  1. Large cash deposit up frontPayment demanded before materials arrive or work starts, especially without a receipt.
  2. No written contractScope, price and timeline agreed only verbally or over chat messages.
  3. Titles that can’t be checkedAn “Eng.” prefix or company name that doesn’t appear on the ERB or URSB registers.
  4. No building permitAdvice to start before plans are approved by the Mbale City building committee.
  5. Long silencesWeeks without site activity or replies, followed by new requests for money.
  6. Shifting explanationsEach missed date comes with a new reason, but no revised written schedule.

Before you build in Mbale

Use these four checks before signing or paying a deposit, whether you’re hiring a builder or an engineer in Uganda.

Check before you pay

Official Ugandan bodies where you can confirm a company, an engineer or a building permit, and raise concerns about building work.

Let down by a builder?

  1. Stop further paymentsDon’t pay more until the work already paid for is done and checked.
  2. Gather your recordsKeep the contract, receipts, messages and dated site photos together.
  3. Put it in writingSend a dated written request setting out what is owed and a deadline.
  4. Get adviceSpeak to a lawyer, and report unsafe or unapproved work to the city building committee.